项目经理看到项目章程中一长串假设与约束,感到无从下手。他希望透彻分析项目需求、复杂性与不确定性,以理解潜在挑战与风险。项目经理应采取哪项行动?
A project manager sees a long list of assumptions and constraints in the project charter and feels overwhelmed. The project manager wants to thoroughly analyze project requirements, complexities, and uncertainties to understand potential challenges and risks. Which action should the project manager take?
选项
- A.Review similar past projects to identify which potential issues should be prioritized
- B.Conduct a collaborative session with all involved stakeholders to assess the project components
- C.Focus on cost estimation first as other aspects are easier to manage and control
- D.Consult with technical experts and gather their feedback as valuable input
解析
解析:约束与不确定性众多的项目需要集体研判。与所有相关方开展协作研讨,能汇聚多元视角、暴露隐藏风险、厘清假设,这是仅靠历史数据或技术专家难以达到的。
Rationale:Projects with many constraints and uncertainties require collective sense-making. A collaborative session with all involved stakeholders brings diverse perspectives, surfaces hidden risks, and clarifies assumptions—more than historical data or technical experts alone can achieve.