题目
项目 PV 5 万、EV 4.5 万、AC 5.5 万美元,成本绩效指数 CPI 是多少?
Your project has PV = $50,000, EV = $45,000, and AC = $55,000. What is the cost performance index (CPI)?
选项
- A.1.22
- B.0.82
- C.0.90
- D.1.10
解析
解析:CPI = EV ÷ AC = 45000 ÷ 55000 ≈ 0.82,低于 1 表示超支。
Rationale:CPI = EV / AC = 45,000 / 55,000 = 0.82. Below 1.0 means over budget.
同考点练习题
-
PMP202611-022 · 答案 B
-
PMP202611-046 · 答案 B
-
PMP202611-120 · 答案 A
-
PMP202611-170 · 答案 B
-
PMP202611-256 · 答案 A
-
PMP202611-291 · 答案 D
-
PMP202611-359 · 答案 B
-
PMP202611-396 · 答案 C