待办列表与优先级 · PMP 练习题解析

敏捷与混合实践 困难 Process 过程域 题号 PMP202611-536

题目

敏捷中,产品待办列表由谁拥有并排序?
In agile, the product backlog is owned and prioritized by the:

选项

  1. A.Scrum Master
  2. B.Development team
  3. C.Product owner
  4. D.Project sponsor
正确答案:C

解析

解析:产品负责人拥有待办列表,按价值排序以最大化团队交付的成果。 Rationale:The product owner owns the backlog, ordering items by value to maximize what the team delivers.