题目
组织正在推行 AI 辅助项目排程,资深项目经理因担心失去掌控而抵触。要在团队中推动这一变革,你首先应该:
Your organization is rolling out AI-assisted project scheduling. Senior PMs resist, fearing loss of control. To lead this change in your team, you should FIRST:
选项
- A.Acknowledge concerns, demonstrate how AI augments rather than replaces their judgment, and pilot it on low-risk work
- B.Mandate AI tool usage immediately
- C.Report resisters to leadership
- D.Abandon the rollout
解析
解析:引领 AI 采用要正面回应恐惧:证明它是增强、在低风险处跑出效果,让信任从体验中生长出来。
Rationale:Leading AI adoption requires addressing fears directly: show AI as augmentation, prove value on low-risk pilots, and let trust build through experience.