项目治理与PMO · PMP 练习题解析

整合管理 中等 Process 过程域 题号 PMP202611-533

题目

项目采用混合方式。敏捷子团队希望完全自治,却总是错过与预测型子团队的集成里程碑。你该怎么做?
Your project uses a hybrid approach. The agile sub-team wants full autonomy but keeps missing integration milestones with the predictive sub-team. What should you do?

选项

  1. A.Establish shared integration cadence and interface agreements both sub-teams commit to
  2. B.Let the agile team remain fully autonomous
  3. C.Convert the whole project to predictive
  4. D.Disband the agile sub-team
正确答案:A

解析

解析:混合项目需要显式集成点:共同节奏加接口约定,既保留敏捷自治又兑现集成承诺。 Rationale:Hybrid projects need explicit integration points: shared cadence and interface agreements let the agile team stay autonomous while meeting integration commitments.