商业环境与战略 困难 Business Environment 商业环境域 题号 PMP202611-270

题目

某组织正在进行数字化转型。项目经理负责技术落地,变革经理负责人员层面。项目经理发现目标业务部门存在明显抵触。项目经理应该怎么做?
An organisation is undergoing a digital transformation. A project manager is asked to lead the technology implementation while a change manager handles the people side. The project manager notices significant resistance in the target business units. What should the project manager do?

选项

  1. A.Raise the resistance as a project risk in the risk register and continue with the technical implementation.
  2. B.Delay the technical delivery until the change manager resolves the resistance issues.
  3. C.Focus only on the technology delivery and leave all resistance issues to the change manager.
  4. D.Collaborate closely with the change manager, share observations about resistance patterns, and jointly develop strategies to address adoption barriers, since technology delivery and change adoption are interdependent.
正确答案:D

解析

解析:D 正确。Business Environment 考查的是:项目成功需要效益实现,而技术若无人采纳就不会产生效益。项目经理与变革经理必须协作,因为技术交付节奏直接影响变革采纳。各自为政(C)很可能交付一个技术完备却无人使用的系统;只登记风险(A)不够,需要主动协作;推迟交付(B)过度保守,还可能引发其他问题。 Rationale:D is correct. Business Environment questions test understanding that project success requires benefits realisation, and technology without adoption produces no benefit. Collaboration between the PM and change manager is essential because technical delivery timing directly affects change adoption. Siloed delivery (C) risks a technically complete but unused system. Risk register only (A) is insufficient: active collaboration is needed. Delaying delivery (B) is overly cautious and may create other issues.