题目
面对有抵触情绪的相关方,项目经理首先应该做什么?
When dealing with a resistant stakeholder, what should the project manager do first?
选项
- A.Exclude them from project updates
- B.Understand their concerns and address them
- C.Ask the sponsor to remove them from the stakeholder list
- D.Communicate only when necessary
解析
解析:积极倾听和主动接触,常能把抵触的相关方转变为支持者。
Rationale:Active listening and proactive engagement often transform resistant stakeholders into supportive participants.
同考点练习题
-
PMP202611-025 · 答案 B
-
PMP202611-070 · 答案 C
-
PMP202611-124 · 答案 C
-
PMP202611-194 · 答案 B
-
PMP202611-228 · 答案 B
-
PMP202611-270 · 答案 D
-
PMP202611-442 · 答案 A
-
PMP202611-507 · 答案 A