商业环境与战略 中等 Business Environment 商业环境域 题号 PMP202611-033

题目

面对有抵触情绪的相关方,项目经理首先应该做什么?
When dealing with a resistant stakeholder, what should the project manager do first?

选项

  1. A.Exclude them from project updates
  2. B.Understand their concerns and address them
  3. C.Ask the sponsor to remove them from the stakeholder list
  4. D.Communicate only when necessary
正确答案:B

解析

解析:积极倾听和主动接触,常能把抵触的相关方转变为支持者。 Rationale:Active listening and proactive engagement often transform resistant stakeholders into supportive participants.