商业环境与战略 中等 Business Environment 商业环境域 题号 PMP202611-124

题目

一个实施新企业资源计划(ERP)系统的项目即将进入推广阶段。多位部门负责人表示抵触,因为其团队未参与需求收集。项目经理首先应该做什么?
A project to implement a new enterprise resource planning (ERP) system is entering the rollout phase. Several department heads express resistance because their teams were not involved in requirements gathering. What should the project manager do first?

选项

  1. A.Proceed with the rollout as planned since the sponsor approved the requirements
  2. B.Delay the rollout until all department heads formally agree to the new system
  3. C.Engage the resistant stakeholders to understand their concerns and develop a targeted change management plan
  4. D.Ask the sponsor to mandate adoption through an executive directive
正确答案:C

解析

解析:组织变革管理要求主动接触抵触的相关方并回应其顾虑,首先应弄清抵触的根因;高管强制令可能带来表面服从,却无法建立成功落地所需的认同。 Rationale:Organizational change management requires engaging resistant stakeholders and addressing concerns proactively. Understanding the root cause of resistance comes first; executive mandates may force compliance but do not build the buy-in needed for successful adoption.