题目
你的项目将替换财务团队使用了 15 年的报表工具。多名财务人员公开表示不会使用新系统,参加培训的人也寥寥无几。你应该怎么做?
Your project will replace a reporting tool the finance team has used for 15 years. Several finance staff say openly that they will not use the new system, and few attend training. What should you do?
选项
- A.Ask HR to make training mandatory and track attendance.
- B.Assess the finance team’s concerns and culture, then work with their leaders on a change plan that involves users early.
- C.Delay the rollout until the finance team is ready.
- D.Launch on schedule and deal with adoption problems later.
解析
解析:考纲要求评估组织文化与变革影响后再行动。让领导者和用户参与能促进接受度。强制培训也许能坐满教室,却赢不了人心;忽视抵触将危及预期收益。
Rationale:The ECO asks you to assess organizational culture and the impact of change, then act. Involving leaders and users builds adoption. Forced training may fill the room, but it will not win people over. If you ignore the pushback, the benefits are at risk.