题目
某组织正从瀑布式转向敏捷。你的团队难以适应新的角色与做法。项目经理应该怎么做?
An organization is transitioning from Waterfall to Agile. Your team struggles to adapt to new roles and practices. What should the project manager do?
选项
- A.Ask the team to continue using the old process
- B.Document the issue and wait for HR intervention
- C.Mentor the team and support training for the Agile transition
- D.Replace the team with experienced Agile professionals
解析
解析:支持组织变革是项目经理的重要职责,在方法论转型期间尤为如此。
Rationale:Supporting organizational change is a key responsibility of the project manager, especially during methodology transitions.