项目中期,领导层宣布重组,团队担心职位稳定,专注度受到影响。项目经理应该怎么做?
Mid-project, leadership announces a reorganisation that worries your team about job security and is hurting focus. What should the project manager do?
选项
- A.Tell the team not to worry and to keep working.
- B.Communicate openly about what is known and unknown and advocate for the team.
- C.Avoid the topic since it is outside project scope.
- D.Share every rumour you hear so the team stays informed.
解析
解析:坦诚沟通加上为团队发声,能稳住焦虑的团队,是富有同理心的服务型领导做法。叫人别担心等于否定真实恐惧;回避会让传言填补空白;传播未经证实的消息会损害可信度。
Rationale:Honest, transparent communication plus advocacy steadies an anxious team and is the empathetic, servant-leader response. Telling them not to worry dismisses real fear; avoidance lets rumours fill the vacuum; passing on unverified rumours erodes credibility.