组织变革与采用 · PMP 练习题解析

商业环境与战略 中等 Business Environment 商业环境域 题号 PMP202611-194

题目

网点员工抵触新的贷款系统,仍继续使用旧表格。最好的做法是什么?
Branch staff are resisting a new loan system and continue to use old spreadsheets. What is the best approach?

选项

  1. A.Disable the spreadsheets immediately.
  2. B.Support organisational change through clear communication of the reasons, training and change champions in each branch.
  3. C.Report the staff to their managers.
  4. D.Wait for them to adapt.
正确答案:B

解析

解析:人们理解原因并获得支持时才愿意改变。培训加本地推动者能降低恐惧;单纯强制往往催生绕行做法和隐性抵触。 Rationale:People adopt change when they understand why and feel supported. Training plus local champions reduces fear; force alone tends to create workarounds and hidden resistance.