题目
某项目将影响 500 名员工的日常工作流。技术交付进展正常,但变革管理计划尚未编制,距上线还有 3 个月。最大的风险是什么?
A project manager is working on a project that will affect 500 employees' daily workflows. The technical delivery is on track but the change management plan has not been developed. The go-live date is in 3 months. What is the most significant risk?
选项
- A.Without a change management plan, user adoption will be inadequate: 500 employees will receive a system they were not prepared for, leading to resistance, workarounds, productivity loss and potential failure to realise intended benefits.
- B.The technical delivery will be delayed due to the missing change management plan.
- C.Training can be delivered in the week before go-live to compensate for the missing plan.
- D.The go-live date will need to be extended by 3 months to develop the change management plan.
解析
解析:A 正确。大规模工作流变更中,变革管理不是可选项——它决定了交付的系统能否真正被采纳。缺少认知、意愿、知识、能力与巩固(ADKAR 模型),500 人面对新系统必然抵触。最大的风险是因采纳不足导致效益无法实现。技术交付(B)是另一类风险;若现在加快变革管理,未必需要推迟 3 个月(D);仅靠上线前一周培训(C)对 500 人的工作流变更远远不够。
Rationale:A is correct. For large-scale workflow changes, change management is not optional: it is what converts a delivered system into an adopted one. Without awareness, desire, knowledge, ability and reinforcement (the ADKAR model), 500 employees receiving a new system will resist it. The most significant risk is benefits non-realisation due to poor adoption. Technical delivery (B) is a separate risk. A 3-month extension (D) may not be necessary if change management is accelerated now. Last-week training (C) is vastly insufficient for a 500-person workflow change.