AI 与技术治理 中等 Business Environment 商业环境域 题号 PMP202611-532

题目

AI 编程助手开始承担团队大量交付物的起草,部分开发觉得自身专业被贬值。作为项目负责人,最佳动作是:
An AI coding assistant is now drafting large portions of the team's deliverables. Some developers feel their expertise is devalued. As project lead, your BEST action is to:

选项

  1. A.Ban the AI tool to protect morale
  2. B.Let the team sort it out naturally
  3. C.Redefine roles around AI-augmented work: humans own review, judgment, and accountability
  4. D.Replace the developers with prompt engineers
正确答案:C

解析

解析:在 AI 增强的团队里要重塑角色分工:AI 负责起草,人负责判断、评审与担责,价值感与士气才能保住。 Rationale:Leading AI-augmented teams means reshaping roles so humans own judgment, review, and accountability while AI handles drafting — this preserves value and morale.