产品负责人在冲刺期间不断加范围。Scrum Master 最恰当的回应是:
During sprint planning, the product owner keeps adding scope mid-sprint. The BEST response from the Scrum Master is to:

选项

  1. A.Accept the changes to please the customer
  2. B.Ask the team to work overtime
  3. C.Cancel the sprint
  4. D.Coach the product owner to prioritize changes for future sprints
正确答案:D

解析

解析:Scrum Master 通过辅导产品负责人把变更放入待办、留给后续冲刺,从而保护当前冲刺目标。 Rationale:The Scrum Master protects the sprint goal by coaching the product owner to queue changes in the backlog for upcoming sprints rather than disrupting the current one.