某组织一直采用传统项目管理,一名项目经理被分配到一个正在进行的项目。组织刚刚开始引入敏捷方法。部分团队成员认为团队缺乏关键领域专业能力,且沟通不足。项目经理应如何回应这些担忧?
A project manager in an organization that uses traditional project management is assigned to an ongoing project. The organization has just begun adopting agile approaches. Some team members believe that key subject matter expertise is lacking and that the team does not communicate enough. How should the project manager respond to these concerns?
选项
- A.Employ third-party specialists to fill the knowledge gap
- B.At the next standup meeting, emphasize the importance of collaboration to the entire team
- C.Add cross-functional internal resources and explain their value to the team
- D.Start using Kanban boards instead of Gantt charts so that work co-dependencies become obvious to everyone
解析
解析:敏捷团队需要 T 型、跨职能的成员,他们认同跨职能协作的价值。补充有能力的跨职能内部资源,同时解决专业能力缺口与沟通问题;单纯强调协作或更换工具都无法弥补能力缺口。
Rationale:Agile teams rely on T-shaped, cross-functional members who recognize the value of cross-functional collaboration. Adding qualified cross-functional internal resources addresses both the expertise gap and the communication concern, whereas training alone or a tool swap does not close the capability gap.