Scrum 角色与职责 · PMP 练习题解析

敏捷与混合实践 中等 Process 过程域 题号 PMP202611-255

题目

产品负责人在冲刺执行期间经常联系不上,导致开发团队只能自行假设需求,而这些假设在冲刺评审时被否决。解决该问题的最佳做法是什么?
A Product Owner is frequently unavailable during sprint execution, causing the development team to make assumptions about requirements that are later rejected during sprint review. What is the best approach to resolve this?

选项

  1. A.Have the Scrum Master make product decisions on behalf of the PO when they are unavailable.
  2. B.The Scrum Master should discuss the impact of PO unavailability on sprint outcomes with the PO and their management, and establish agreed-upon availability commitments.
  3. C.Allow the team to continue making assumptions and document them for sprint review discussion.
  4. D.Have the development team delay work on ambiguous items until the PO is available.
正确答案:B

解析

解析:B 正确。产品负责人可随时对接是 Scrum 的基本要求。Scrum Master 的仆人式领导职责包含清除障碍,产品负责人长期缺席就是结构性障碍。通过恰当渠道建立可用性承诺,才触及根因。Scrum Master 不应代做产品决策(A),那会破坏问责分工;继续假设(C)让问题延续;停摆等(D)无谓牺牲冲刺速率。 Rationale:B is correct. PO availability is a fundamental Scrum requirement. The Scrum Master's servant-leadership role includes removing impediments, and an unavailable PO is a structural impediment. Escalating through the appropriate channels to establish availability commitments addresses the root cause. The Scrum Master should not make product decisions (A). That violates the accountability separation. Continuing with assumptions (C) perpetuates the problem. Delaying work (D) kills sprint velocity unnecessarily.