Scrum 角色与职责 · PMP 练习题解析

敏捷与混合实践 中等 Process 过程域 题号 PMP202611-290

题目

某 Scrum 团队已进入“高效期”。Scrum Master 发现多数仪式已不再需要自己引导。此时应把重心放在哪里?
A Scrum team has reached the "performing" stage. The Scrum Master notices the team no longer needs facilitation for most ceremonies. What should the Scrum Master focus on?

选项

  1. A.Shift focus to organisational impediments, continuous improvement opportunities beyond the team, and coaching the team toward even greater autonomy.
  2. B.Begin planning the Scrum Master's transition off the team to free up capacity.
  3. C.Continue facilitating all ceremonies to maintain consistency and prevent regression.
  4. D.Reduce involvement significantly since the team no longer needs a Scrum Master.
正确答案:A

解析

解析:A 正确。高效团队依然受益于 Scrum Master,但重心从内部引导转向体系性障碍、组织层辅导与持续改进,角色由“主持人”变为“战略资产”。继续过度引导(C)会让团队长不大;完全退出(D)丢掉宝贵辅导;规划退出(B)误解了这一角色的演进。 Rationale:A is correct. A high-performing team still benefits from a Scrum Master, but the focus shifts from internal facilitation to systemic impediments, organisational coaching and continuous improvement. The Scrum Master becomes a strategic asset rather than a facilitator. Continuing to over-facilitate (C) infantilises the team. Complete withdrawal (D) removes valuable coaching. Planning exit (B) misunderstands the evolving Scrum Master role.