题目
某 Scrum 团队已进入“高效期”。Scrum Master 发现多数仪式已不再需要自己引导。此时应把重心放在哪里?
A Scrum team has reached the "performing" stage. The Scrum Master notices the team no longer needs facilitation for most ceremonies. What should the Scrum Master focus on?
选项
- A.Shift focus to organisational impediments, continuous improvement opportunities beyond the team, and coaching the team toward even greater autonomy.
- B.Begin planning the Scrum Master's transition off the team to free up capacity.
- C.Continue facilitating all ceremonies to maintain consistency and prevent regression.
- D.Reduce involvement significantly since the team no longer needs a Scrum Master.
解析
解析:A 正确。高效团队依然受益于 Scrum Master,但重心从内部引导转向体系性障碍、组织层辅导与持续改进,角色由“主持人”变为“战略资产”。继续过度引导(C)会让团队长不大;完全退出(D)丢掉宝贵辅导;规划退出(B)误解了这一角色的演进。
Rationale:A is correct. A high-performing team still benefits from a Scrum Master, but the focus shifts from internal facilitation to systemic impediments, organisational coaching and continuous improvement. The Scrum Master becomes a strategic asset rather than a facilitator. Continuing to over-facilitate (C) infantilises the team. Complete withdrawal (D) removes valuable coaching. Planning exit (B) misunderstands the evolving Scrum Master role.
同考点练习题
-
PMP202611-064 · 答案 B
-
PMP202611-084 · 答案 C
-
PMP202611-094 · 答案 D
-
PMP202611-122 · 答案 B
-
PMP202611-163 · 答案 B
-
PMP202611-169 · 答案 B
-
PMP202611-255 · 答案 B
-
PMP202611-311 · 答案 B