题目
项目进入最后一个阶段,需要采用敏捷方法。讨论阶段工作时,部分成员表示自己从未做过敏捷项目,而截止日期已迫在眉睫。项目经理应如何处理?
During the last phase of a project, an agile approach is required. While discussing the phase, some team members reveal that they have never worked with agile before. The deadline is approaching fast. What should the project manager do in this situation?
选项
- A.File a change request that addresses the agile training that members lack
- B.Escalate this as an issue to the project sponsor because it is a company-wide problem and a blocker
- C.Ask team members who have agile experience to mentor the others
- D.Identify and provide the most cost-effective agile training for the team members
解析
解析:培训是建立所需能力最可靠的方式,培训成本可纳入资源与成本计划。导师制虽好,但在紧迫的工期下可能来不及补齐技能;上报也不能解决能力缺口。
Rationale:Providing training is the most reliable way to build the required capability, and training costs can be reflected in the resource and cost plans. Mentoring is useful but may be too slow under a tight deadline, and escalation does not solve the skill gap.
同考点练习题
-
PMP202611-064 · 答案 B
-
PMP202611-084 · 答案 C
-
PMP202611-122 · 答案 B
-
PMP202611-163 · 答案 B
-
PMP202611-169 · 答案 B
-
PMP202611-255 · 答案 B
-
PMP202611-290 · 答案 A
-
PMP202611-311 · 答案 B