敏捷与混合实践 中等 Process 过程域 题号 PMP202611-064

题目

冲刺期间,团队无法完成全部待办条目。他们应该怎么做?
During a sprint, the team cannot complete all backlog items. What should they do?

选项

  1. A.Work overtime
  2. B.Ask the Product Owner to reprioritize backlog items
  3. C.Remove testing activities
  4. D.Extend the sprint duration
正确答案:B

解析

解析:敏捷团队应与产品负责人协作调整优先级,而不是牺牲质量或冲刺周期。 Rationale:Agile teams collaborate with the Product Owner to adjust priorities without compromising quality or sprint timelines.