题目
冲刺期间,团队无法完成全部待办条目。他们应该怎么做?
During a sprint, the team cannot complete all backlog items. What should they do?
选项
- A.Work overtime
- B.Ask the Product Owner to reprioritize backlog items
- C.Remove testing activities
- D.Extend the sprint duration
解析
解析:敏捷团队应与产品负责人协作调整优先级,而不是牺牲质量或冲刺周期。
Rationale:Agile teams collaborate with the Product Owner to adjust priorities without compromising quality or sprint timelines.