职业道德与合规 困难 Business Environment 商业环境域 题号 PMP202611-525

题目

政府客户的合规审计发现你方 AI 模型的训练数据缺少授权文件,项目已完成 80%。最佳做法是:
A government client's compliance audit finds your AI model's training data lacks consent documentation. The project is 80% complete. BEST action:

选项

  1. A.Ship anyway — it's almost done
  2. B.Delete the model quietly
  3. C.Blame the data vendor publicly
  4. D.Halt affected work, assess remediation via change control, and engage legal/compliance immediately
正确答案:D

解析

解析:合规问题必须立即止损:停掉受影响工作、让法务介入、经变更控制重排计划。 Rationale:Compliance findings demand immediate containment: stop affected work, engage legal, and replan through change control.