冲刺进行中,客户要求团队立刻加入一个新功能。应该怎么处理?
During a sprint, a customer asks the team to add a new feature right away. What should happen?
选项
- A.The team adds it to the current sprint.
- B.The product owner adds it to the product backlog and prioritises it for a future sprint.
- C.The project manager rejects it.
- D.The team cancels the sprint.
解析
解析:冲刺期间应保持冲刺目标稳定。新需求进入产品待办列表,由产品负责人按价值排序,团队可在后续冲刺中拉取。
Rationale:The sprint goal should stay stable during a sprint. New needs go to the product backlog where the product owner orders them by value; the team can pull them in a later sprint.