题目
两个风险:风险 A(60% × 1 万)与风险 B(20% × 4 万)。预算只够一份应对计划,优先哪个?
Two risks: Risk A (60% × $10k) and Risk B (20% × $40k). With budget for only one response plan, which risk gets priority?
选项
- A.Risk B, higher EMV ($8,000 vs $6,000)
- B.Risk A, higher probability
- C.Neither — probabilities are too low
- D.Both equally
解析
解析:EMV:A=6000,B=8000。只能二选一时按 EMV 排序,B 的期望影响更大。
Rationale:EMV: A = $6,000, B = $8,000. Prioritize by EMV when forced to choose; B's expected impact is greater.