Scrum 角色与职责 · PMP 练习题解析

敏捷与混合实践 中等 Process 过程域 题号 PMP202611-122

题目

在冲刺评审中,产品负责人以交付功能不符合验收标准为由否决了两个用户故事,而开发团队认为工作已经完成。Scrum Master 应该怎么做?
During a sprint review, the Product Owner rejects two user stories because the delivered functionality does not match the acceptance criteria, even though the development team believes the work is complete. What should the Scrum Master do?

选项

  1. A.Override the Product Owner's decision since the development team completed the technical work
  2. B.Facilitate a discussion between the Product Owner and the development team to clarify the acceptance criteria gaps, then move the stories back to the product backlog for refinement
  3. C.Escalate the disagreement to the project sponsor for a final decision
  4. D.Ask the development team to fix the rejected stories during the next sprint without adding them to the sprint backlog
正确答案:B

解析

解析:用户故事是否满足完成定义与验收标准,最终由产品负责人决定。Scrum Master 的职责是促进沟通与流程,而不是推翻决定或上报;被拒故事应退回产品待办列表重新估算与排序,且工作不应在冲刺待办列表之外进行。 Rationale:The Product Owner has final authority on whether a story meets the Definition of Done and acceptance criteria. The Scrum Master facilitates communication and process rather than overriding or escalating; rejected stories return to the product backlog for re-estimation and prioritization, and work is never done outside the sprint backlog.