题目
产品负责人每个冲刺只参加一次会议,团队常常要等好几天才能得到答复。你应该怎么做?
The product owner attends only one meeting per sprint, and the team often waits days for answers. What should you do?
选项
- A.Make the decisions for the product owner.
- B.Discuss the impact with the product owner and agree on regular availability or a delegate with authority.
- C.Complain to the sponsor.
- D.Let the team guess the requirements.
解析
解析:产品负责人不可用属于障碍。说明影响并协商解决方案才能解决根因;让团队猜需求只会带来返工。
Rationale:An unavailable product owner is an impediment. Showing the impact and agreeing a solution addresses the cause; guessing requirements creates rework.