冲刺目标之所以重要,是因为它:
A sprint goal is important because it:
选项
- A.Pleases the sponsor
- B.Gives the sprint a coherent purpose and allows flexibility in scope details
- C.Is required by law
- D.Replaces the product backlog
解析
解析:冲刺目标提供目的与凝聚力,团队可在细节上灵活调整而不跑偏。
Rationale:The sprint goal provides purpose and coherence, letting the team adapt scope details while staying focused.