题目
某远程成员绩效下滑。在认定其消极怠工之前,项目经理应先考虑:
A remote team member's performance has dropped. Before assuming disengagement, the project manager should consider:
选项
- A.Possible isolation, unclear expectations, or personal challenges — and check in privately
- B.They are looking for another job
- C.They need a pay cut
- D.They should be moved on-site
解析
解析:远程环境下绩效下滑常源于孤立或期望不清,私下沟通才能诊断出真实原因。
Rationale:Performance drops often stem from isolation or unclear expectations in remote settings; a private check-in diagnoses the real cause.
同考点练习题
-
PMP202611-001 · 答案 B
-
PMP202611-026 · 答案 B
-
PMP202611-027 · 答案 A
-
PMP202611-034 · 答案 A
-
PMP202611-088 · 答案 A
-
PMP202611-098 · 答案 C
-
PMP202611-099 · 答案 B
-
PMP202611-143 · 答案 A