管理团队:绩效与冲突 · PMP 练习题解析

资源管理 中等 People 人域 题号 PMP202611-517

题目

某远程成员绩效下滑。在认定其消极怠工之前,项目经理应先考虑:
A remote team member's performance has dropped. Before assuming disengagement, the project manager should consider:

选项

  1. A.Possible isolation, unclear expectations, or personal challenges — and check in privately
  2. B.They are looking for another job
  3. C.They need a pay cut
  4. D.They should be moved on-site
正确答案:A

解析

解析:远程环境下绩效下滑常源于孤立或期望不清,私下沟通才能诊断出真实原因。 Rationale:Performance drops often stem from isolation or unclear expectations in remote settings; a private check-in diagnoses the real cause.