题目
发起人问项目如何支撑公司的数字化转型战略。最佳回答应引用:
The sponsor asks how the project supports the company's digital transformation strategy. The BEST answer references:
选项
- A.The team's favorite tools
- B.The project logo
- C.Traceability from project objectives and benefits to strategic goals
- D.Meeting minutes
解析
解析:把项目成果追溯到组织战略与价值交付,才能证明战略契合。
Rationale:Strategic alignment is demonstrated by tracing project outcomes to organizational strategy and value delivery.