题目
项目经理在站会上发现两名成员因任务归属争执。最恰当的第一步是:
A project manager notices two team members arguing about task ownership during a stand-up meeting. What is the BEST first action?
选项
- A.Reassign the task to a third team member
- B.Escalate the issue to the project sponsor
- C.Listen to both perspectives and facilitate a discussion
- D.Document the conflict in the risk register
解析
解析:先弄清双方立场再行动;引导讨论才能触及根因,草率改派或上报只是回避问题。
Rationale:The project manager should first understand both sides before acting. Facilitating discussion addresses the root cause; reassigning or escalating prematurely avoids the real issue.
同考点练习题
-
PMP202611-001 · 答案 B
-
PMP202611-026 · 答案 B
-
PMP202611-027 · 答案 A
-
PMP202611-034 · 答案 A
-
PMP202611-088 · 答案 A
-
PMP202611-098 · 答案 C
-
PMP202611-099 · 答案 B
-
PMP202611-143 · 答案 A