管理团队:绩效与冲突 · PMP 练习题解析

资源管理 困难 People 人域 题号 PMP202611-511

题目

项目经理在站会上发现两名成员因任务归属争执。最恰当的第一步是:
A project manager notices two team members arguing about task ownership during a stand-up meeting. What is the BEST first action?

选项

  1. A.Reassign the task to a third team member
  2. B.Escalate the issue to the project sponsor
  3. C.Listen to both perspectives and facilitate a discussion
  4. D.Document the conflict in the risk register
正确答案:C

解析

解析:先弄清双方立场再行动;引导讨论才能触及根因,草率改派或上报只是回避问题。 Rationale:The project manager should first understand both sides before acting. Facilitating discussion addresses the root cause; reassigning or escalating prematurely avoids the real issue.