题目
有成员提议用 AI 从项目文档生成风险登记册初稿。项目经理应当:
A team member proposes using AI to generate the draft risk register from project documents. The project manager should:
选项
- A.Reject AI use as unreliable
- B.Allow it as a starting draft, then have the team review, validate, and own the final register
- C.Let the AI finalize it unsupervised
- D.Ban all AI tools
解析
解析:AI 能加快起草,但风险内容必须由团队评审并负责——AI 产出始终需要人工校验。
Rationale:AI accelerates drafting, but the team must review and own risk content — AI output always needs human validation.