题目
某职能经理不断把团队成员抽调去做日常运营工作。最佳做法是:
A functional manager keeps pulling your team members onto operational work. The BEST approach is to:
选项
- A.Negotiate resource commitments and clarify priorities with the functional manager
- B.Escalate to the CEO immediately
- C.Accept it as normal
- D.Reassign the project work to contractors
解析
解析:与职能经理协商能从源头解决资源冲突,同时维护合作关系。
Rationale:Negotiating with the functional manager addresses the resource conflict at its source while preserving the working relationship.