虚拟团队横跨四个时区,成员反映彼此疏离。哪种做法最能建立团队凝聚力?
A virtual team spans four time zones and members complain they feel disconnected. Which approach BEST builds team cohesion?
选项
- A.Require everyone to attend all meetings live
- B.Replace meetings with email updates
- C.Establish overlapping core hours and rotate meeting times fairly
- D.Assign all critical work to one time zone
解析
解析:核心时段重叠加公平轮换会议时间,兼顾包容性与可行性;强求全部实时参会会拖垮远地成员。
Rationale:Overlapping core hours with fairly rotated meeting times balances inclusion and practicality; requiring all-live attendance burns out distant members.