题目
监管机构把产品审批推迟了 6 个月,项目其他方面已就绪。最佳应对是:
Regulatory approval for your product is delayed 6 months by the agency. The project is otherwise ready. The BEST response is to:
选项
- A.Launch without approval
- B.Blame the agency publicly
- C.Disband the team
- D.Use integrated change control to replan: assess options like phased rollout or scope adjustments with the sponsor
解析
解析:外部延误要走变更控制:与发起人重新规划选项,而不是违规上市或全线停摆。
Rationale:External delays go through change control: replan options with the sponsor rather than launching illegally or freezing.
同考点练习题
-
PMP202611-103 · 答案 D
-
PMP202611-176 · 答案 C
-
PMP202611-240 · 答案 B
-
PMP202611-261 · 答案 A
-
PMP202611-347 · 答案 B
-
PMP202611-357 · 答案 B
-
PMP202611-458 · 答案 B
-
PMP202611-494 · 答案 D