进度监控与恢复 · PMP 练习题解析

进度管理 中等 Process 过程域 题号 PMP202611-516

题目

监管机构把产品审批推迟了 6 个月,项目其他方面已就绪。最佳应对是:
Regulatory approval for your product is delayed 6 months by the agency. The project is otherwise ready. The BEST response is to:

选项

  1. A.Launch without approval
  2. B.Blame the agency publicly
  3. C.Disband the team
  4. D.Use integrated change control to replan: assess options like phased rollout or scope adjustments with the sponsor
正确答案:D

解析

解析:外部延误要走变更控制:与发起人重新规划选项,而不是违规上市或全线停摆。 Rationale:External delays go through change control: replan options with the sponsor rather than launching illegally or freezing.