题目

召开冲刺回顾会的目的是:
A sprint retrospective is held to:

选项

  1. A.Inspect the team's process and identify improvements
  2. B.Demonstrate the product to stakeholders
  3. C.Plan the next sprint's work
  4. D.Estimate story points
正确答案:A

解析

解析:回顾会专注过程改进:哪些做得好、哪些不好、要改什么。 Rationale:Retrospectives focus on process improvement — what worked, what didn't, and what to change.