题目
团队章程的主要目的是:
The primary purpose of a team charter is to:
选项
- A.Document the project budget
- B.List all project risks
- C.Define the product scope
- D.Establish team values, agreements, and operating guidelines
解析
解析:团队章程记录团队共同认可的价值观、基本规则、沟通规范与决策流程。
Rationale:A team charter captures values, ground rules, communication norms, and decision processes the team agrees to follow.