一位来自不同文化的成员在会上从不直接表达不同意见。为确保其声音被听见,项目经理应:
A team member from a different culture avoids direct disagreement in meetings. To ensure their input is heard, the project manager should:

选项

  1. A.Call on them publicly to state their position
  2. B.Offer multiple feedback channels, such as anonymous input or one-on-one check-ins
  3. C.Assume silence means agreement
  4. D.Exclude them from decision meetings
正确答案:B

解析

解析:具备文化敏感度的领导者会提供多种沟通渠道,让所有人都能自在发声。 Rationale:Culturally sensitive leaders provide varied communication channels so all voices can contribute comfortably.