活动估算与估算精度 · PMP 练习题解析

进度管理 中等 Process 过程域 题号 PMP202611-478

题目

两个团队对同一功能的估算分别是 3 点和 13 点。最佳下一步是:
Two teams estimate the same feature at 3 and 13 story points. The BEST next step is:

选项

  1. A.Average them to 8
  2. B.Take the lower estimate
  3. C.Discuss assumptions together (e.g., planning poker) until the gap is understood, then re-estimate
  4. D.Escalate to management
正确答案:C

解析

解析:估算差距大说明假设不同,用结构化讨论把假设挖出来再重估,才是正解。 Rationale:Wide estimate gaps signal different assumptions; structured discussion (planning poker) surfaces them before re-estimating.