题目
在什么情况下 EAC 按 BAC / CPI 计算?
EAC is calculated as BAC / CPI when:
选项
- A.The project is ahead of schedule
- B.The budget was wrong from the start
- C.Current variances are expected to continue into the future
- D.Management wants a lower number
解析
解析:BAC/CPI 假设当前成本绩效趋势延续,是“典型偏差”情形下的标准 EAC 公式。
Rationale:BAC/CPI assumes the current cost performance trend continues — the standard 'typical' EAC formula.
同考点练习题
-
PMP202611-004 · 答案 C
-
PMP202611-298 · 答案 A
-
PMP202611-302 · 答案 A
-
PMP202611-504 · 答案 D
-
PMP202611-641 · 答案 D