完工预测:EAC/ETC/TCPI/VAC · PMP 练习题解析

成本管理 中等 Process 过程域 题号 PMP202611-477

题目

在什么情况下 EAC 按 BAC / CPI 计算?
EAC is calculated as BAC / CPI when:

选项

  1. A.The project is ahead of schedule
  2. B.The budget was wrong from the start
  3. C.Current variances are expected to continue into the future
  4. D.Management wants a lower number
正确答案:C

解析

解析:BAC/CPI 假设当前成本绩效趋势延续,是“典型偏差”情形下的标准 EAC 公式。 Rationale:BAC/CPI assumes the current cost performance trend continues — the standard 'typical' EAC formula.