题目
项目用故事点估算。相比按小时估算,故事点的主要优势是:
A project uses story points for estimation. The MAIN advantage over hour estimates is that story points:
选项
- A.Are more precise
- B.Eliminate the need for planning
- C.Guarantee deadlines
- D.Measure relative size/complexity, reducing pressure and gaming
解析
解析:故事点只衡量相对工作量,避免“工时承诺”带来的虚假精确与压力。
Rationale:Story points estimate relative effort, avoiding the false precision and pressure of hour-based commitments.
同考点练习题
-
PMP202611-323 · 答案 C
-
PMP202611-346 · 答案 B
-
PMP202611-379 · 答案 C
-
PMP202611-654 · 答案 A