敏捷估算与故事点 · PMP 练习题解析

敏捷与混合实践 困难 Process 过程域 题号 PMP202611-479

题目

项目用故事点估算。相比按小时估算,故事点的主要优势是:
A project uses story points for estimation. The MAIN advantage over hour estimates is that story points:

选项

  1. A.Are more precise
  2. B.Eliminate the need for planning
  3. C.Guarantee deadlines
  4. D.Measure relative size/complexity, reducing pressure and gaming
正确答案:D

解析

解析:故事点只衡量相对工作量,避免“工时承诺”带来的虚假精确与压力。 Rationale:Story points estimate relative effort, avoiding the false precision and pressure of hour-based commitments.