定义活动与活动清单 · PMP 练习题解析

进度管理 中等 Process 过程域 题号 PMP202611-475

题目

渐进明细意味着:
Progressive elaboration means:

选项

  1. A.Adding team members gradually
  2. B.Delaying all decisions
  3. C.Elaborate reporting
  4. D.Developing plans in greater detail as more information becomes available
正确答案:D

解析

解析:渐进明细是随不确定性下降不断细化计划——规划是持续的,不是一次性的。 Rationale:Progressive elaboration iteratively refines plans as uncertainty decreases — planning is continuous, not one-time.