Scrum 事件与仪式 · PMP 练习题解析

敏捷与混合实践 困难 Process 过程域 题号 PMP202611-465

题目

团队在第 7 天就完成了 10 天冲刺的全部条目。他们应该:
The team finished all sprint backlog items by day 7 of a 10-day sprint. They should:

选项

  1. A.Start the next sprint early
  2. B.Take 3 days off
  3. C.Pull in ready backlog items in collaboration with the product owner
  4. D.Add unplanned features
正确答案:C

解析

解析:在与产品负责人协作下,拉入下一批优先级最高且已就绪的事项,既保持流动又不打乱范围。 Rationale:With PO collaboration, the team pulls the next highest-priority ready items — maintaining flow without scope chaos.

同考点练习题