团队在第 7 天就完成了 10 天冲刺的全部条目。他们应该:
The team finished all sprint backlog items by day 7 of a 10-day sprint. They should:
选项
- A.Start the next sprint early
- B.Take 3 days off
- C.Pull in ready backlog items in collaboration with the product owner
- D.Add unplanned features
解析
解析:在与产品负责人协作下,拉入下一批优先级最高且已就绪的事项,既保持流动又不打乱范围。
Rationale:With PO collaboration, the team pulls the next highest-priority ready items — maintaining flow without scope chaos.