一名高绩效成员希望承担一项超出其专长的拓展性任务。最佳回应是:
A high-performing team member asks for a stretch assignment outside their expertise. The BEST response is to:
选项
- A.Refuse to protect the schedule
- B.Assign it without support to test them
- C.Assign it with mentoring support and clear success criteria
- D.Give it to a more senior member instead
解析
解析:带辅导的拓展任务能同时提升能力与动机,明确成功标准则可控住风险。
Rationale:Stretch assignments with mentoring grow capability and motivation; clear success criteria keep the risk managed.