题目
SPI 为 0.85、CPI 为 1.1,说明项目:
Your SPI is 0.85 and CPI is 1.1. This means the project is:
选项
- A.Behind schedule and over budget
- B.Ahead of schedule and under budget
- C.Ahead of schedule but over budget
- D.Behind schedule but under budget
解析
解析:SPI 小于 1 表示进度落后;CPI 大于 1 表示低于预算(创造的价值高于花掉的钱)。
Rationale:SPI < 1 means behind schedule; CPI > 1 means under budget (earning more value than cost).
同考点练习题
-
PMP202611-022 · 答案 B
-
PMP202611-046 · 答案 B
-
PMP202611-120 · 答案 A
-
PMP202611-170 · 答案 B
-
PMP202611-256 · 答案 A
-
PMP202611-291 · 答案 D
-
PMP202611-359 · 答案 B
-
PMP202611-396 · 答案 C