题目
项目进展正常,但市场变化使最初的商业论证不再成立。最佳做法是:
A project is on track, but a market shift makes its original business case obsolete. The BEST action is to:
选项
- A.Reassess the business case and benefits with the sponsor; recommend pivot or termination if value is gone
- B.Continue — sunk costs must be recovered
- C.Hide the market shift from stakeholders
- D.Accelerate to finish before anyone notices
解析
解析:商业论证失效时,应与发起人重估价值;继续做没有价值的项目只会浪费资源。
Rationale:When the business case no longer holds, reassess value with the sponsor — continuing a valueless project wastes resources.