题目
一项增加功能的变更请求已获批准。首先必须更新什么?
A change request to add a feature is approved. What must be updated FIRST?
选项
- A.The team roster
- B.The company website
- C.The scope baseline and project management plan components
- D.Nothing — just do the work
解析
解析:获批变更要经整体变更控制先更新基准与计划,再付诸实施。
Rationale:Approved changes update baselines and plans through integrated change control before implementation.