题目
你的预测型项目需求不确定性很高,发起人却坚持固定总价、固定范围合同。最恰当的建议是:
Your predictive project faces high uncertainty in requirements. The sponsor insists on a fixed-price, fixed-scope contract. The BEST advice is to:
选项
- A.Recommend a hybrid/agile-friendly contract type or phased approach, explaining the risk of fixed scope under uncertainty
- B.Accept without question
- C.Double the budget silently
- D.Start work and hope
解析
解析:高不确定下锁定范围容易失败;适配敏捷或分阶段的合同能让商务条款贴合现实。
Rationale:Fixed scope under high uncertainty invites failure; agile-friendly or phased contracts align commercial terms with reality.