题目
Scrum 中的产品待办列表是:
The product backlog in Scrum is:
选项
- A.Fixed at project start
- B.An emergent, ordered list of everything needed in the product
- C.Owned by the developers
- D.A detailed project schedule
解析
解析:待办列表是动态浮现并持续细化的,由产品负责人按价值排序。
Rationale:The backlog is emergent and continuously refined; the product owner orders it by value.