题目
你负责的预测型施工项目必须加装一套公司历史上首次使用的 AI 安全监控系统。最佳交付方式是:
Your predictive construction project must add an AI-based safety monitoring system — a first for the company. The BEST delivery approach is:
选项
- A.Pure predictive — it's construction
- B.Pure agile for everything
- C.Delay the AI system indefinitely
- D.A hybrid approach: predictive for construction work, agile iterations for the AI system where uncertainty is high
解析
解析:混合正适合“确定性不一”的场景:成熟的工作用预测型,探索性的 AI 系统用迭代/敏捷。
Rationale:Hybrid fits mixed certainty: predictive where work is well-understood, iterative/agile where the AI system is exploratory.