团队建设与团队章程 · PMP 练习题解析

资源管理 中等 People 人域 题号 PMP202611-447

题目

团队刚组建,成员彼此客气但不愿质疑别人的想法。按塔克曼模型,团队处于哪个阶段?
Your team is newly formed and members are polite but hesitant to challenge ideas. According to Tuckman's model, the team is in which stage?

选项

  1. A.Norming
  2. B.Performing
  3. C.Forming
  4. D.Adjourning
正确答案:C

解析

解析:形成期的典型特征是相互客气、依赖领导者、不愿表达分歧——成员还在彼此磨合定位。(原题标注为规范期,与塔克曼模型定义不符,此处按模型定义取形成期。) Rationale:Forming is characterized by politeness, dependence on the leader, and reluctance to voice disagreement as members orient themselves.