项目管理计划与整合规划 · PMP 练习题解析

整合管理 中等 Process 过程域 题号 PMP202611-445

题目

项目管理计划是:
The project management plan is:

选项

  1. A.Written only by the sponsor
  2. B.The consolidated document defining how the project is executed, monitored, and closed
  3. C.Optional for agile projects
  4. D.A marketing brochure
正确答案:B

解析

解析:项目管理计划整合了各子计划与各基准,是执行阶段的首要指导文件。 Rationale:The project management plan integrates all subsidiary plans and baselines; it is the primary execution guide.